Procurement Management and Road Construction Project Perfomance in Uganda National Roads Authority

dc.contributor.authorNAKONDE, Zaituni
dc.contributor.authorBasheka, Benon(Supervisor)
dc.contributor.authorOluka, Pross(Supervisor)
dc.date.accessioned2017-07-25T07:16:06Z
dc.date.available2017-07-25T07:16:06Z
dc.date.issued2012-02
dc.descriptionA Dissertation submitted to the Higher Degrees Department in partial fulfillment of the requirements for the award of the Master’s Degree in Management Studies (Project Planning and Management) of Uganda Management Instituteen_US
dc.description.abstractThis study was focused on examining the effect of procurement management on road construction projects perfomance in Uganda National Roads Authority. The study was premised on the assumption that the prevalent poor performance of the road construction projects in Uganda National Roads Authority could be explained by three dimensions of procurement management namely: procurement planning, procurement organization and procurement control. The study adopted a cross sectional case study design, data was collected from 71 people of the following categories; UNRA Directors, Project Managers, Project/Station Engineers, Procurement Officers, Contracts Committee Members, Senior staff of Supervising Consultants and Senior Staff of the Contractors. Data was collected using questionnaires, interview guides and Documentary checklist and were analyzed using descriptive statistics and inferential statistics. The study empirically revealed that procurement management explain a total variance of 22.4% in the performance of road construction projects in Uganda National Roads Authority, with procurement planning explaining only 2.2 %, procurement organization explaining 9% and procurement control explaining 11.2 %. The study then concludes that procurement organization and control have a significant effect on the performance of the road construction projects in Uganda National Roads Authority. Although the study revealed that there was a very small effect of procurement planning on road construction project performance, it is recommended that improvement in some aspects of the procurement planning is necessary. Under procurement organisation and project performance, it is recommended that UNRA should endeavour to improve the aspects of role and obligation definition and ensure that all the players in the project implementation abide by their roles and obligations. Lastly it is recommended that that UNRA through its departments should ensure adequate designs and specifications, close supervision and monitoring as well as limiting the scope changes and adhering to contractsen_US
dc.identifier.citationAPAen_US
dc.identifier.other10/MMSPPM/22/036
dc.identifier.urihttp://hdl.handle.net/20.500.12305/216
dc.language.isoenen_US
dc.publisherUganda Management Instituteen_US
dc.subjectProcurement Managementen_US
dc.subjectRoad Construction Project Performanceen_US
dc.subjectUganda National Roads Authorityen_US
dc.titleProcurement Management and Road Construction Project Perfomance in Uganda National Roads Authorityen_US
dc.typeBooken_US

Files

Original bundle

Now showing 1 - 1 of 1
Loading...
Thumbnail Image
Name:
Zaituni' final dessertation.pdf
Size:
1.21 MB
Format:
Adobe Portable Document Format
Description:
fulltext

License bundle

Now showing 1 - 1 of 1
No Thumbnail Available
Name:
license.txt
Size:
1.71 KB
Format:
Item-specific license agreed upon to submission
Description:

Collections